Laos, China Launch 500-kV Interconnection Project
The project includes the construction of a new 500-kV substation in Laos, a 183.5-km cross-border transmission line linking Namor in Oudomxay, Laos, with Xishuangbanna in Yunnan,
The project includes the construction of a new 500-kV substation in Laos, a 183.5-km cross-border transmission line linking Namor in Oudomxay, Laos, with Xishuangbanna in Yunnan,
The Chinese and Lao sections of the China-Laos 500-kV power interconnection project were physically connected on Thursday, marking a major step forward in bringing the project into
The transmission system includes a new 500 kV Namor 3 substation located in Namor district, Oudomxay Province of Lao PDR which links to the 500 kV Xishuangbanna power station in Jinghong
A groundbreaking ceremony for the China-Laos 500 kV Interconnection Project was held in the Lao capital of Vientiane on February 26, 2025.
Phoxay Sayasone, Laos'' Minister of Energy and Mines, explained that the system will connect Laos'' power grid with neighboring countries, including Thailand, Vietnam, Cambodia,
Work began on the Lao section of the China-Laos 500 kV power interconnection project on February 26 in the capital, Vientiane. Once operational, the project will significantly enhance the
A drone assists during the line-connecting operation of the Chinese and Lao sections of the China-Laos 500-kV power interconnection project on Feb. 5, 2026. The Chinese and Lao sections of the China